Demolition and Foundation for building extension

We transform your perception into great results.

Demolition and Foundation for building extension

Execution of demolition and new continuous footing foundations to prepare for a multi-directional building expansion.

Type: Commercial
Manager: Lurs
Category: Extension
Area: Calgary, Alberta

Manager Comment

The start of our expansion! Demolition cleared the way, and our team did an excellent job with the footing and rebar installation. Despite being close to the existing structure, the foundation pour went smoothly. We’re locked in and ready to vertical!

713c1dc44dbea0d1e07b6e82da90e9a5_1773890061_9324.png
713c1dc44dbea0d1e07b6e82da90e9a5_1773889983_7499.jpg713c1dc44dbea0d1e07b6e82da90e9a5_1773890000_1794.jpg
713c1dc44dbea0d1e07b6e82da90e9a5_1773890003_0272.jpg
713c1dc44dbea0d1e07b6e82da90e9a5_1773890005_4612.jpg




 

This project phase focused on the initial site preparation and foundation work required to extend the building footprint on multiple sides.

    - Targeted Demolition: The existing pavement was saw-cut and broken. Foundations for a previous solarium were removed to clear the zone for new structural load points.

    - Excavation and Rebar Preparation: Trenches were excavated for the new continuous footings. Grade beams and footing rebar were fabricated and tied to engineer specifications to support the new walls.

    - Footing and Foundation Pour: Concrete was poured into the trenches to form the base footings. Rebar dowels were left projecting to tie into the next vertical phase.

    - Slab Preparation and Pour: The existing ground was prepared and graded. New main slabs were framed, reinforced with mesh, and poured to provide a level slab-on-grade for the expansion areas. This included framing for new linear features.

    - Structural Connection (I-Beam): A structural steel I-beam was integrated and connected (welded) into the new foundation system, providing essential support and tying the new structure to the old. This demonstrates heavy load transfers in the expansion plan.